Senior Center Improvements

 Florence Douglas Senior Center Improvements 

Project Allocation: $ 109,150
 Amount Expended: 100%
Votes: 860   Voting finish among 12 projects approved: #10
Project Description:
Install emergency lighting, new flooring and energy efficient windows.

Implementing Entity:
Public Works Department, City of Vallejo

Vinyl floor was removed and replaced with a tile floor in the kitchen area; plumbing issues were addressed and repaired, windows were replaced with double-pane, energy-efficient glass, dry rot was repaired, the HVAC system was replaced, and emergency/exit signs were installed.

 Resolution No. 13-121 N.C.
 Resolution No. 13-138 N.C.
 Original Project Proposal