Mare Island Western Approach

Mare Island Causway BridgeSummary:

The Mare Island Causeway western approach structure is located on “G” Street at the westerly end of the Mare Island Causeway Bridge, originally built in 1934.

The existing western approach is a three-span timber framed structure with two intermediate bents that have been supplemented with temporary shoring to address significant structural deterioration and stress deficiencies.

The proposed replacement bridge is an estimated 52 foot long simple span concrete structure. The purpose of this project is to permanently address the deterioration, stress deficiencies and increase the safety of the traveling public. The project will improve load capacity as well as improve seismic characteristics.

The proposed project includes replacement of approach road asphalt concrete (AC) pavement, sidewalk and installation of new handrails, signing and striping. The work will be broken into two phases.  Please see the Staged Construction Plan for more information.

Traffic pattern during Construction period: One-way traffic onto Mare Island over Causeway & exiting Mare Island thru SR-37.

Budget: $3.5 M Engineer’s Estimate

Status: Construction Bid Adversised

Schedule

  • February 2015 - Bid Opening
  • April 2015 - Project Award
  • May 2015 - Construction Begin

Project Documents

Go to the following location to access project files.  Visit the bids and proposals page for the most current proposal.

If you have questions contact Srinivas Muktevi, Project Manager (707) 651-7107, Srinivas.Muktevi@cityofvallejo.net