Print Page

SR2S Hogan School Site Improvements


Install pedestrian countdown signal heads, lighted crosswalk with LED Pedestrian Warning lights (IRWL) and other traffic calming mesures at Georgia St., Oakwood Ave., Rosewood Ave. and Westwood St.

Cost: $724K Engineer's Estimate
$450K Construction Contract

Status: Under Construction


  • February 7, 2013 - Project Advertisement
  • February 26, 2013 – Bid Opening
  • June 13, 2013 - Construction Starts (public notice)

Project Documents

Go to the following location to access project files.

If you have questions contact Srinivas Muktevi, Project Manager (707) 651-7107,